Network Device Replacement
Scheduled Maintenance Report for 4Schools
Completed
We have concluded our unplanned emergency maintenance. The replacement of the affected network device was successfully completed and service has returned back to normal. Thank you for your patience and understanding while we undertook this work this evening.
Posted Feb 23, 2017 - 01:26 CST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 22, 2017 - 23:45 CST
Scheduled
Following a failed network device, we are going to be undergoing emergency unplanned maintenance to install a replacement network device. There will be downtime affecting some of our servers during this time. The maintenance is expected to last no more than 2 hours.
Posted Feb 22, 2017 - 23:33 CST